Construction of Upper Trishuli 3 ‘A’ resumes
NUWAKOT, July 30: The construction of the Upper Trishuli 3 ‘A’ Hydro power Project – has resumed.
The contractor company, China Gezhouba Group Corporation along with a team of experts has started preliminary study at Faletar of Manakamana in Nuwakot – the dam area of the project.
Project Chief Fanindra Raj Joshi informed that the Company has started technical tests and assessment of loss caused to the project by the 2015 earthquake.
Currently some 80 Nepali and 20 Chinese workers are mobilized in the project construction area.
The construction of the 60-MW capacity project that started from June 2011 was supposed to be completed on 31 May 2014. RSS